I am scheduling an assignment (duration 4 days) over a period of 5 days (Mon-Fri, stretched assignment), where the Wednesday is a non-working day (leave).
This will create a stretched assignment where the Wednesday is correctly considered as a non-working day.
Now I open the Service Order (via IW32) and change any fields contents and save, the change can be as small as entering an extra . in the SO description. When going back to MRS I will refresh the planning board and can then see the assignment bar shrinking as if Wednesday now is a working day.
In other words, it seems like updating the SO triggers a recalculation of the end time of the assignment where non-working hours are not taken into consideration.
Has any of you encountered this problem before?
Or can anyone point out a note or another possible solution for this issue?
I have searched through notes/customizing configuration for hours but without any luck.
Thanks in advance.