Hi Rajen,

 

Thank you very much for providing the clarity. Rewarded the point.

 

1. Include Dependent Requirements (Check Box):

Dependent Requirements are generated due to a planned receipt, for example as generated by planned orders.You will also find the same as an MRP element in OMD5 SB Dep Req. (Requirement Element, negative).

 

Q1: In OMD5, i could not see any negative indicator for SB (refer screen shot below):

 

OMD5.png

 

 

3. Include dependent reservations (Drop Down- X - Include All reservations): Dependent Reservations are generated due to a fixed receipt, for example as generated by production orders. The dependentrequirements can be 'withdrawable', when the production order is in released state or not withdrawable, such as in created state, but not released. When you mention 'X' here, all the reservations (created + released) are taken into account). This is a Requirement Element, negative.

 

Q2: In the above statement, you mentioned as "Dependent Requirements". Is this "Dependent Requirement" or "Dependent Reservation"?

 

Q3: What is "Dependent Reservations can be withdrawable"? Is it mean that production order components (BOM items) can be consumed / issued using 261 movement type?

 

Thanks


 


 